Page 1:
Nova programme · Steering committee
Minutes of the meeting of 22 September 2026
2. Data migration
The first dry-run migration was carried out on 1 September. The reject rate reaches 18%...
Decision: the second dry-run migration is rescheduled to 19 October 2026.
3. North site pilot
Decision: the North site pilot cutover date is kept on 5 October 2026.
| Lot | Budget | Used | Left | Progress |
|---|---|---|---|---|
| L2 · Configuration | 240 | 236 | 6 | 98% |
| L3 · Data migration | 120 | 131 | 45 | 70% |
| L4 · Acceptance | 90 | 84 | 12 | 92% |
| L5 · Training | 45 | 30 | 15 | 65% |
| L6 · North pilot | 50 | 0 | 50 | 0% |
Page 3:
Key milestones
September · Data migrated and accepted
5 October · North site pilot cutover
Cutover condition: two successful dry-run migrations, the last one validated at least 10 business days before.
Is the schedule on track?
No. The pilot cutover is kept on 05/10, but dry-run migration no. 2 has been rescheduled to 19/10: the cutover condition set at launch can no longer be met.
| Item | Planned | Actual | Gap | Source |
|---|---|---|---|---|
| Cutover condition | 2 dry-run migrations, the last 10 business days before | Only 1, 18% rejects | Not met on 05/10 | pptx p.3 · docx |
| Dry-run migration no. 2 | Before cutover | Rescheduled to 19/10 | 14 days after cutover | pdf p.1 · docx |
| Data migration | 120 d | 131 d used, 45 d remaining | +56 d (+47%) | xlsx |
| September milestone | Data migrated and accepted | Neither | Missed | pptx p.3 · xlsx |
To decide before 05/10: postpone the cutover, or revise the condition.